Our planning for 0.6 is now at the point of a rough draft, not yet benefitting from individual estimates or completed designs.
Overall development schedule
Currently filling out a plan for design and development of 0.6. Draft timeline:
Activity | Start | Length |
Design, planning, estimates (and some early development) | April 1 | 4 weeks |
Development for milestone 0.5.03 | May 2 | Until projected tasks complete (estimate 4 weeks) |
Integration and test | (estimated) May 30 | 1 week |
Development for milestone 0.5.04 | (estimated) June 6 | Until projected tasks complete (estimate 4 weeks) |
More development, undefined | No estimate | Until feature complete for all of 0.6 |
Bug fix and release | No estimate | Until zero bugs |
Plan by team, Milestone 0.5.03 and 0.5.04
Application
Services and Build
- BrianKirsch: i18n (0.5.03), IMAP folder storage and synchronization (0.5.04)
- HeikkiToivonen: SSL & TLS improvements (accepting certs) (0.5.03), integrate WebDAV ACL (0.5.04)
- GrantBaillie: WebDAV synch/share layer (Zanshin) development, testing and integration, tickets (0.5.03); ETag support (0.5.04)
- JeffreyHarris: Recurrence proposal and implementation (0.5.03); timezones proposal and implementation (0.5.04)
- MorgenSagen: Sharing via publishing workflows, account management tweaks, merging changed shared items (0.5.03); sharing termination, CalDAV-esque event sharing, use of tickets (0.5.04)
- PhillipEby: Item collection input, Python Schema API (core content model and parcels) proposal and implementation (0.5.03)
- MikeT: Subversion move, wxWidgets and other import upgrades, (0.5.03) instrumentation framework (0.5.04), tinderbox and release issues, weekly builds (ongoing)
Repository & Dev Platform
- TedLeung: Item collections, notifications
- AndiVajda: Repository performance
Postponed Features
- FreeBusyExploration
- JunkMailManagement
-- LisaDusseault - 09 Dec 2004