Date | Milestones | Bug | Other | Status | Project |
Aug 6 - Aug 10 |
Aug 6 | Run Book first draft | Bug#10196 | run book | Done | Hub |
Aug 6 | OSAF website pushed out | Bug#10040 | | Done | Preview |
Aug 6 | Desktop 0.7 Zero Bug Release | | | | Desktop |
Aug 8 | Server 0.7 code dependent branding/docs | Bug#9953 | waiting on final copy review | Done | Server |
Aug 9 | Server 0.7 Zero Bug Release (Code Complete) | | | | Server |
Aug 10 | Move Hub to new hardware | Bug#10195 | Jared to walk through procedures with Bear and Randy | Done | Hub |
Aug 13 - Aug 17 |
Aug 13 | Troubleshooting page ready for final review | Bug#10344 | Troubleshooting | | Preview |
Aug 13 | Release docs ready for final review | Bug#9459, Bug#9608, Bug#9557 | Release notes, Known Issues | | Preview |
Aug 13 | OSAF docs ready for final review | Bug#9545, Bug#10335 | Vision Document, OSAF FAQ | | Preview |
Aug 13 | Product docs ready for final review | Bug#9553, Bug#9546 | Product FAQ, Feature List | | Preview |
Aug 13 | Guides ready for final review | Bug#9549, Bug#9544 | Get Started Guide, Screencasts | | Preview |
Aug 13 | Hub re-branding ready for final review | Bug#10226 | TOS links, About box, Activation Email | Done | Hub |
Aug 13 | Desktop 0.7 release | | | | Desktop |
Aug 14 | KKIE Test Session | | | | Preview |
Aug 16 | Server 0.7 release | | | | Server |
Aug 17 | Server announcements | | Jared: lists, blog, freshmeat | | Server |
Aug 20 - Aug 24 |
Aug 20 | OSAF docs complete | | Vision Document, OSAF FAQ | | Preview |
Aug 20 | Product docs complete | | Product FAQ, Feature List | | Preview |
Aug 20 | Guides complete | | Get Started Guide, Screencasts | | Preview |
Aug 20 | Release docs complete | | Release notes, Known Issues | | Preview |
Aug 20 | Troubleshooting page complete | | Troubleshooting | | Preview |
Aug 20 | Terms of Service, Privacy Policy ready for final review | | | | Hub |
Aug 20 | Run Book ready for final review | Bug#10196 | run book | | Hub |
Aug 20 | Hub re-branding final | | | | Hub |
Aug 20 | Hub updated to 0.7 | | | | Hub |
Aug 20 | Hub announcement | | Jared: lists, blog | | Hub |
Aug 27 - 31 |
Aug 27 | Terms of Service, Privacy Policy complete | | | | Hub |
Aug 27 | NOC Run Book complete | | | | Hub |
Aug 27 | Hub Preview Launch | | | | Hub |
Aug 27 | Desktop announcement | | Philippe: lists, blog, freshmeat, cheeseshop | | Desktop |
Aug 27 | Preview announcement | | Katie: lists, blog | | Preview |
Sept 3 - 7 |
Sept 3 | Week 1 | | | | Preview |
Sept 5 | Hub updated to 0.7.1 | | Tentative date | | Hub, Server |
Sept 10 - 14 |
Sept 10 | Week 2 | | | | Preview |
Sept 12 | Hub updated to 0.7.2 | | Tentative date | | Hub, Server |
Sept 17 - 21 |
Sept 17 | Week 3 | | | | Preview |
Sept 19 | Hub updated to 0.7.3 | | Tentative date | | Hub, Server |
Sept 21 | Launch party | | Tentative date | | Preview |
Sept 24 - 28 |
Sept 24 | Week 4 | | | | Preview |
Sept 24 | Stability assessment | | Cast wider net of attention | | Preview |
Sept 24 | Desktop 0.7.1 Release | | Tentative date | | Desktop |
Sept 26 | Hub updated to 0.7.4 | | Tentative date | | Hub, Server |
Date | Milestones | Dependencies | Other | Status | Project |
Jan 20 - 26 | Jan 24 - Place production server order | | | Done | Hub |
Jan 27 - Feb 2 | Feb 2 - Prepare Preview countdown list - schedule weekly meeting | | | Done | Preview |
Feb 3 - 9 | Feb 9 - Finalize brand name | Pending report from trademark attorney | | Done | Preview |
Feb 10 - 16 | Feb 16 - Chandler sharing branch to land | Pending Morgen schedule | | Done | Desktop |
| Feb 16 - Cosmo 0.6.1/Chandler 0.7 preliminary integration testing starts | | | Done | Server |
Feb 17 - 23 | Feb 20 - Cosmo work on 0.7 branch starts | | | Done | Server |
| Feb 20 - Cosmo work on 0.6.1 branch starts | | | Done | Server |
Feb 24 - Mar 2 | Feb 27 - Cosmo 0.6 release | | 0.6 Plan | Done | Server |
| Feb 28 - osaf.us updated with Cosmo 0.6 (with data migration) | | | Done | Server |
| Feb 28 - QA - certify Cosmo 0.6 on osaf.us | | | Done | Server |
| Feb 28 - Cosmo 0.6 launch - announcements & docs | | | Done | Server |
| Feb 28 - Final domain name secured | | | Done | Preview |
| Mar 2 - Product names finalized | Closing on brand name | | Done | Preview |
| Mar 2 - Domain name finalized | Closing on brand name | | Done | Preview |
Mar 3 - 9 | Mar 6 - Terms of Service 1st draft | | | Done | Hub |
Mar 31 - Apr 6 | Apr 2 - Metrics infrastructure running regularly to product updates | | | Done | Hub |
Apr 7 - 13 | Apr 9 - Production hardware up at colo | | | Done | Hub |
| Apr 9 - Chandler 0.7 feature freeze | | | Done | Desktop |
| Apr 10 - Start of dedicated desktop performance work | | | Done | Desktop |
| Apr 10 - Start of PPD design review period for app | | | Done | Desktop |
| Apr 10 - Cosmo 0.6.1/Chandler 0.7 developer integration testing period | | | Done | Server |
Apr 14 - 20 | Apr 16 - Work on final web presence content starts | Some of this has already been in progress | | Started | Preview |
| Apr 16 - Cosmo 0.6.1 QA and integration test period | | | Done | Preview |
Apr 21 - 27 | Apr 23 - Final logo ready for approval | | | Done | Desktop |
| Apr 27 - Desktop 0.7 formal bug fixing period starts | | | Started | Desktop |
Apr 28 - May 4 | May 1 - osaf.us also available via final domain name | | | Done | Hub |
| May 1 - Final decisions on site technologies | | | Done | Preview |
May 5 - 11 | May 8 - Cosmo 0.6.1 launch - announcements | | | Done | Server |
May 12 - 18 | May 14 - Final logos ready for re-skinning the apps | | | Done | Server |
| May 17 - Desktop performance work milestone - end | | | Done | Desktop |
| May 17 - Design review milestone - end | | | Done | Desktop |
| May 15 - Cosmo 0.6.1 release | | | Done | Server |
| May 16 - hub.chandlerproject.org updated to Cosmo 0.6.1 | | | Done | Server |
| May 18 - QA - certify Cosmo 0.6.1 on osaf.us | | | Done | Server |
May 26 - Jun 1 | May 30 - Chandler 0.7 user performance evaluation | | | Done | Server |
Jun 2 - 8 | Jun 4 - Cosmo 0.6.1 on hub.chandlerproject.org official launch announcement | | | Done | Hub |
| Jun 4 - Chandler 0.7 dogfooding and migration checkpoint ready | | | Done | Server |
| Jun 6 - hub.chandlerproject.org official launch | | | Done | Hub |
| Jun 28 - Cosmo 0.7 feature freeze | | | Done | Server |
Jun 23 - 29 | Jun 25 - Product site architecture/hierarchy complete | | | Done | Preview |
Jun 30 - Jul 6 | Jul 1 - Final visual design for product site pages - web presence | | | Done | Preview |
Jul 20 | Implement all domain redirects | | Bug#9978 | Done | Hub |
| Jul 9 - Localization freeze : Last day for string changes (use en_US po after that date) | | | Done | Desktop |
Jul 14 - 20 | Jul 16 - Chandler 0.7 code complete | | | Done | Desktop |
| Jul 16 - Redirect cosmo.osafoundation.org | | | Done | Preview |
| Jul 23 - Update QA sharing to some RC | | Bug#9833 | Done | Preview |