Preview Release Countdown

This is meant to be the central page for managing all the final deliverables for the Preview release covering all products. The following are bugzilla queries to track all the documentation, branding and code-dependent deliverables.

Bug Tracking Tables

OSAF: Assignee by Project | Assignee by Target Milestone | Assignee by Priority
Non-Code Deliverables: Assignee by Target Milestone | Assignee by Component

Milestones and Dates | Subscribe to the Countdown Calendar.

Date Milestones Bug Other Status Project
Aug 6 - Aug 10
Aug 6 Run Book first draft Bug#10196 run book Done Hub
Aug 6 OSAF website pushed out Bug#10040   Done Preview
Aug 6 Desktop 0.7 Zero Bug Release       Desktop
Aug 8 Server 0.7 code dependent branding/docs Bug#9953 waiting on final copy review Done Server
Aug 9 Server 0.7 Zero Bug Release (Code Complete)       Server
Aug 10 Move Hub to new hardware Bug#10195 Jared to walk through procedures with Bear and Randy Done Hub
Aug 13 - Aug 17
Aug 13 Troubleshooting page ready for final review Bug#10344 Troubleshooting   Preview
Aug 13 Release docs ready for final review Bug#9459, Bug#9608, Bug#9557 Release notes, Known Issues   Preview
Aug 13 OSAF docs ready for final review Bug#9545, Bug#10335 Vision Document, OSAF FAQ   Preview
Aug 13 Product docs ready for final review Bug#9553, Bug#9546 Product FAQ, Feature List   Preview
Aug 13 Guides ready for final review Bug#9549, Bug#9544 Get Started Guide, Screencasts   Preview
Aug 13 Hub re-branding ready for final review Bug#10226 TOS links, About box, Activation Email Done Hub
Aug 13 Desktop 0.7 release       Desktop
Aug 14 KKIE Test Session       Preview
Aug 16 Server 0.7 release       Server
Aug 17 Server announcements   Jared: lists, blog, freshmeat   Server
Aug 20 - Aug 24
Aug 20 OSAF docs complete   Vision Document, OSAF FAQ   Preview
Aug 20 Product docs complete   Product FAQ, Feature List   Preview
Aug 20 Guides complete   Get Started Guide, Screencasts   Preview
Aug 20 Release docs complete   Release notes, Known Issues   Preview
Aug 20 Troubleshooting page complete   Troubleshooting   Preview
Aug 20 Terms of Service, Privacy Policy ready for final review       Hub
Aug 20 Run Book ready for final review Bug#10196 run book   Hub
Aug 20 Hub re-branding final       Hub
Aug 20 Hub updated to 0.7       Hub
Aug 20 Hub announcement   Jared: lists, blog   Hub
Aug 27 - 31
Aug 27 Terms of Service, Privacy Policy complete       Hub
Aug 27 NOC Run Book complete       Hub
Aug 27 Hub Preview Launch       Hub
Aug 27 Desktop announcement   Philippe: lists, blog, freshmeat, cheeseshop   Desktop
Aug 27 Preview announcement   Katie: lists, blog   Preview
Sept 3 - 7
Sept 3 Week 1       Preview
Sept 5 Hub updated to 0.7.1   Tentative date   Hub, Server
Sept 10 - 14
Sept 10 Week 2       Preview
Sept 12 Hub updated to 0.7.2   Tentative date   Hub, Server
Sept 17 - 21
Sept 17 Week 3       Preview
Sept 19 Hub updated to 0.7.3   Tentative date   Hub, Server
Sept 21 Launch party   Tentative date   Preview
Sept 24 - 28
Sept 24 Week 4       Preview
Sept 24 Stability assessment   Cast wider net of attention   Preview
Sept 24 Desktop 0.7.1 Release   Tentative date   Desktop
Sept 26 Hub updated to 0.7.4   Tentative date   Hub, Server

Meeting Notes

DONE

Date Milestones Dependencies Other Status Project
Jan 20 - 26 Jan 24 - Place production server order     Done Hub
Jan 27 - Feb 2 Feb 2 - Prepare Preview countdown list - schedule weekly meeting     Done Preview
Feb 3 - 9 Feb 9 - Finalize brand name Pending report from trademark attorney   Done Preview
Feb 10 - 16 Feb 16 - Chandler sharing branch to land Pending Morgen schedule   Done Desktop
  Feb 16 - Cosmo 0.6.1/Chandler 0.7 preliminary integration testing starts     Done Server
Feb 17 - 23 Feb 20 - Cosmo work on 0.7 branch starts     Done Server
  Feb 20 - Cosmo work on 0.6.1 branch starts     Done Server
Feb 24 - Mar 2 Feb 27 - Cosmo 0.6 release   0.6 Plan Done Server
  Feb 28 - osaf.us updated with Cosmo 0.6 (with data migration)     Done Server
  Feb 28 - QA - certify Cosmo 0.6 on osaf.us     Done Server
  Feb 28 - Cosmo 0.6 launch - announcements & docs     Done Server
  Feb 28 - Final domain name secured     Done Preview
  Mar 2 - Product names finalized Closing on brand name   Done Preview
  Mar 2 - Domain name finalized Closing on brand name   Done Preview
Mar 3 - 9 Mar 6 - Terms of Service 1st draft     Done Hub
Mar 31 - Apr 6 Apr 2 - Metrics infrastructure running regularly to product updates     Done Hub
Apr 7 - 13 Apr 9 - Production hardware up at colo     Done Hub
  Apr 9 - Chandler 0.7 feature freeze     Done Desktop
  Apr 10 - Start of dedicated desktop performance work     Done Desktop
  Apr 10 - Start of PPD design review period for app     Done Desktop
  Apr 10 - Cosmo 0.6.1/Chandler 0.7 developer integration testing period     Done Server
Apr 14 - 20 Apr 16 - Work on final web presence content starts Some of this has already been in progress   Started Preview
  Apr 16 - Cosmo 0.6.1 QA and integration test period     Done Preview
Apr 21 - 27 Apr 23 - Final logo ready for approval     Done Desktop
  Apr 27 - Desktop 0.7 formal bug fixing period starts     Started Desktop
Apr 28 - May 4 May 1 - osaf.us also available via final domain name     Done Hub
  May 1 - Final decisions on site technologies     Done Preview
May 5 - 11 May 8 - Cosmo 0.6.1 launch - announcements     Done Server
May 12 - 18 May 14 - Final logos ready for re-skinning the apps     Done Server
  May 17 - Desktop performance work milestone - end     Done Desktop
  May 17 - Design review milestone - end     Done Desktop
  May 15 - Cosmo 0.6.1 release     Done Server
  May 16 - hub.chandlerproject.org updated to Cosmo 0.6.1     Done Server
  May 18 - QA - certify Cosmo 0.6.1 on osaf.us     Done Server
May 26 - Jun 1 May 30 - Chandler 0.7 user performance evaluation     Done Server
Jun 2 - 8 Jun 4 - Cosmo 0.6.1 on hub.chandlerproject.org official launch announcement     Done Hub
  Jun 4 - Chandler 0.7 dogfooding and migration checkpoint ready     Done Server
  Jun 6 - hub.chandlerproject.org official launch     Done Hub
  Jun 28 - Cosmo 0.7 feature freeze     Done Server
Jun 23 - 29 Jun 25 - Product site architecture/hierarchy complete     Done Preview
Jun 30 - Jul 6 Jul 1 - Final visual design for product site pages - web presence     Done Preview
Jul 20 Implement all domain redirects   Bug#9978 Done Hub
  Jul 9 - Localization freeze : Last day for string changes (use en_US po after that date)     Done Desktop
Jul 14 - 20 Jul 16 - Chandler 0.7 code complete     Done Desktop
  Jul 16 - Redirect cosmo.osafoundation.org     Done Preview
  Jul 23 - Update QA sharing to some RC   Bug#9833 Done Preview
toggleopenShow attachmentstogglecloseHide attachments
Topic attachments
I Attachment Action Size Date Who Comment
pdfpdf PreviewCountdown.pdf manage 393.6 K 08 Mar 2007 - 10:20 UnknownUser  
pngpng PreviewCountdown.png manage 152.0 K 19 Mar 2007 - 11:19 UnknownUser  
htmlhtml PreviewCountdown.html manage 2.6 K 19 Mar 2007 - 11:19 UnknownUser  
elsegan PreviewCountdown.gan manage 9.6 K 19 Mar 2007 - 11:19 UnknownUser  
htmlhtml PreviewCountdown-tasks.html manage 16.1 K 19 Mar 2007 - 11:19 UnknownUser  
htmlhtml PreviewCountdown-resources.html manage 2.4 K 19 Mar 2007 - 11:19 UnknownUser  
htmlhtml PreviewCountdown-chart.html manage 2.2 K 19 Mar 2007 - 11:19 UnknownUser  
pngpng PreviewCountdown.res.png manage 8.5 K 19 Mar 2007 - 11:19 UnknownUser  
View topic | Edit |  | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r86 |r84 < r83 < r82 < r81 | More topic actions...
Planning.PreviewReleaseCountdown moved from Projects.PreviewReleaseCountdown on 13 Jul 2007 - 17:51 by MimiYin - put it back
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.